Construction update 04-21-2018

Even though we will be adding the conference room mezzanine, that is not stopping this team from finishing the first goal at hand. Before you know it, cars will be pulling in and the mechanics will be servicing! See below the drone footage of the service area.



Two current BMW of Wilmington technicians excited to check out out the new equipment!


Mirrors are now installed in all restrooms.


Wood doors are installed throughout the sales and service areas.


Water fountains are installed to keep everyone hydrated!


A bike rack is provided for anyone wanting to trade in their two wheels for four!


Upcoming Week Look Ahead:

  • Cleaning of all areas
  • Final paint touches
  • Finishing all flooring throughout the building
  • Begin tackling punch list items in service area
Posted in News, Social