Construction update 05-05-2018

Enjoy the time lapse video at the end of the update viewing the start to current progress. Music chosen by your Project Manager John Breshears, who has spent almost the last year on New Centre Dr!


The automatic slider door separating the sales area into the service drive is powered up!


The overhead doors are also up, running, and ready for cars to drive in for service!


The 2nd floor conference room mezzanine is underway! Structural steel beams have been delivered and installation has started.


We know it’s not a BMW, but we couldn’t resist!


Enjoy the view from ground up of your new BMW of ILM Dealership!


Upcoming Week Look Ahead:

  • Final cleaning continues
  • Conference mezzanine steel continues
  • Exterior owner provided signage continues
  • Continue finishing punch list items
Posted in News, Social