Construction update 06-09-2018

The focus this past week is really pushing the 2nd floor conference room mezzanine. We have removed the temporary protection and began enclosing the space. We are counting down the days as owner furniture will be delivered next week and the move-in process will begin!


Ceilings below the mezzanine are installed.


Concrete has been placed on the stairs and paint applied underneath.


HVAC duct work and units are installed.

The cable railing is installed on the staircase.

The frames and glass are installed to enclose the conference room!


Upcoming Week Look Ahead:

  • Install flooring on stairs and in conference room
  • Final paint
  • Finish all glass install
  • Owner furniture delivered