Construction Update 5/23/2020

Baker Collection

Construction Update 5/23/2020

Exterior glazing began this week at the sales building as DEFS on the covered canopy and metal metal install progressed around the exterior. The sales building also began receiving paint and continued ceiling grid install. Overhead doors were installed on the service building. Mechanical, Plumbing, and Electrical progressed across both buildings while activities outside kicked off. Sub grading of the site and landscape islands are in progress and Duke site lighting install also began.

Sales Building

Highland Roofing began installing interior and exterior metal panel accents.

Clayton Commercial Glazing began installing exterior glazing in the curtainwall this week.

Thank you to all our trade partners for continuing to practice safe social precautions on site!

Nolan Painting began prime and first coats of paint in the back of house and showroom offices.

Grey Interiors continued ceiling grid install while A-1 Mechanical began installing lay-in diffusers.

Outdoor heat pumps have been set by A-1 Mechanical and disconnect switches installed by DPS.

Service Building

Crawford Doors joined the action on site and installed the overhead coiling doors.

DPS completed all in wall in the service building.

Remaining interior wall liner panels were installed throughout the service building bays.

A-1 installed ductwork and the sidewall louver at the service building equipment room as Milam Plumbing continued surface mounted piping.

Site

Duke Energy installed their portion of site lighting pole bases this week.

MSB Development returned to the site to begin sub grading and forming landscape islands for the rear parking area.

Looking Ahead

Sales Building:

  • Complete EIFS and DEFS on exterior and canopy
  • Complete exterior glazing
  • Complete metal panel install
  • Complete ceiling grid install
  • Complete mechanical and electrical overheads
  • Continue interior painting

Service Building:

  • Complete hanging and finishing drywall
  • Complete bathroom ceiling grid install
  • Begin prime paint

Site:

  • Complete curb placement
  • Complete irrigation sleeve install
  • Continue grading

 

 

 

 