Construction Update 7/17/2020

Baker Collection

Construction Update 7/17/2020

Paving kicked off this week on site while both buildings continued to make progress toward the finish line. Sales building received carpet and began window cleaning on the interior and exterior. The service building carwash continues to make progress for final electrical inspection and the photobooth flooring process began.

Sales Building

Carpet and base by Carolina Commercial Floorcovering has been installed in all offices.

Service Building

Lights are on in the handwash bays, service area, and photobooth.

Carwash equipment connections continue by DPS Electrical.

Epoxy floor in the photobooth began its 3 day application process. 2 layers down, 1 to go!

Exterior painting by Nolan Painting began.

Site

Paving across the site completed this week and will be striped after a cool down period.

Baker Collections Drone Flyover

In case you missed it – check out some in progress drone footage!

Looking Ahead

Sales Building:

  • Complete window cleaning
  • Complete final clean
  • Certificate of Occupancy

Service Building:

  • Complete photobooth epoxy floor
  • Complete final clean
  • Electrical final inspection
  • Building final inspection
  • Certificate of Occupancy

Site:

  • Complete pavement markings
  • Zoning inspection

 

Posted in News